A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solution at the meeting, The project manager should()
ATell the customer that he will not address any problems
BTell the customer that the problem is not sufficiently defined to company to a solution
CCollect as much information on the problem without committing his company to a solution
DGive the customer a range of solutions that might be acceptable to his company
正确答案
答案解析
经理与客户的非正式会议上提出一个问题对于项目有重大影响,客户希望开一个专题会议,项目经理应该(72)。A.告诉客户他不会提出任何问题B.告诉客户这个问题是没有充分定义C.收集更多的问题信息决定是否召开专题会议D.给客户几个可能被接受的解决方案