Project manager believes that modifying the project scope may provide added value for the customer. The project manager should ( ) .
A.change the scope baseline
Acontact the customer to determine if the change adds value
Bcall
Cmeeting of the change control board
Dchange the project’s objectives
正确答案
答案解析