Project manager believes that modifying the project scope may provide added value for the customer. The project manager should ( ) .
A.change the scope baseline
Acontact the customer to determine if the change adds value
Bcall
Cmeeting of the change control board
Dchange the project’s objectives
相关试题
-
Project manager believes that modifying the project scope may provide added value for the customer.
-
Project manager believes that modifying the project scop may provide added value for the customer.T
-
A project manager believes that modifying the scope of the project may provide added value service f
-
A project manager believes that modifying the scope of the project may provide added value service f
-
re the project team provide the functionlity the customer expects in a new prece of software, the pr