A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )

Aassign change tasks to project members

Bcall a meeting of the configuration control board

Cchange the scope baseline

Dpostpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline