单选题
Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( )
A.change the scope baseline
Acontact the customer to determine if the change adds value
Bcall
Cmeeting of the change control board
Dchange the project"s objectives
正确答案
答案解析
项目经理认为修改项目范围可以为客户提供增值服务。项目经理应该通知项目变更控制委员会召开会议。