Estimate Activity Duration sis the process of estimating the number of work period sto complete indivities with estimated resources.The tools and technques is not including( ).
Aexpert judgment
Banalogous estimating
Crequirements trace ability matrix
Dthree-point estimating
相关试题
-
Estimate Activity Duration sis the process of estimating the number of work period sto complete ind
-
ations. The cost estimating process considers whether the expectedsavings can offset the cost of the
-
( )estimating is a technique for estimating the duration or cost of an activity ou project using hi