There are strategies typically deal with threats or risks that may have negative impacts on project objectives if they occur. Some other strategies are suggested to deal with risks with potentially positive impacts. ( ) is a risk response strategy that may be adopted for either threats or opportunities.

AShare

BMitigate

CTransfer

DAcceptance