The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .
AChang control board
BProject management office
CProject manager
DConfiguration management officer
正确答案
答案解析
实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。