Developing the project schedule is often an
iterative process. It determines the planned start and finish dates for project
activities and milestones. Schedule development can require the review and
revision of duration estimates and resource estimates to create an approved
project schedule that can serve as a baseline to ( ) progress.
A.analyze
Atrack
Blevel
Cexten
相关试题
-
Developing the project schedule is often an iterative process. It determines the planned start and
-
tes and resource estimates to create an approved () that can serve as a baseline to track progress.
-
tes and resource estimates to create an approved(74)that can serve as a baseline to track progress.
-
) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish
-
and techniques are used in developing schedule. ( ) is a schedule network analysis technique that