单选题
Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
A.PERT
AResource levelling
BSchedule compression
CCritical chain metho
正确答案
答案解析
PERT方法能协调整个计划的各道工序,通过描绘出项目包含的各种活动的先后次序,标明每项活动的时间或相关的成本,合理安排人力、物力、时间、资金,加速计划的完成。(72) A.PERT B.资源平衡 C.进度压缩 D.关键路径法