Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).
A.fast tracking
Awhat-if scenario analysis
Bresource leveling
Ccritical chain metho