A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) .
A.assign change tasks to project members
B.call
A.meeting of the configuration control board
C.change the scope baseline
Apostpone the modification until
Bseparate enhancement project is funde
Cafter this project is complete
Daccording to the original baseline