试题详情

A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) . A.assign change tasks to project members B.call A.meeting of the configuration control board C.change the scope baseline

Apostpone the modification until

Bseparate enhancement project is funde

Cafter this project is complete

Daccording to the original baseline