All of followings should be done by the project manager during project control except (). A.Determine the a change has occurred

AEnsure that a change is agreed

BMake sure all changes are approve

Cby management

DManage changes as they occur

正确答案

答案解析

译文:项目经理不应该在项目控制过程中执行的工作是()。
A)确定变更已经发生
B)确保变更已达成共识
C)确保所有变更都获得管理层批准
D)在变更发生时,对变更进行管理